UPDATE – Elizabethtown Gas Main and Service Line Replacement Project

Elizabethtown Gas has informed the Borough they will be installing gas service lines on North Greenwood Ave beginning Monday, June 23, 2025

This work will begin at the northern end of North Greenwood Ave, near Washington Ave.

It is anticipated the installation of new service lines to the homes between Washington Ave and Hart Ave will take approximately 7 days to complete.

Elizabethtown Gas will be working its way south along North Greenwood Ave. to Broad St.

IMPORTANT: If you have not done so already, please be sure to respond to Elizabethtown’s request to schedule your gas service line replacement.

Although Elizabethtown Gas is responsible for the coordination and management of this project, please feel free to contact our Administrator Doug Walker on 609-466-2636 or via email at doug.walker@hopewellboro-nj.us should you have any questions.